2nd unit of Payra power plant resumes after 2 months

BSS
Published On: 07 Jan 2025, 17:01
Photo:BSS

PATUAKHALI, Jan 7, 2025 (BSS) - The second unit of Payra 1320-megawatt (MW) Thermal Power Plant resumed production on Monday night after two months.

After completing repairing, the authority resumed the production around 9.30 pm on Monday (6 January), said Shah Abdul Mawla, Plant Manager of Payra 1320 MW Thermal Power Plant, this morning.

The electricity production of the power plant was shut down for maintenance on November 9 last year.

Now the plant will supply 10 percent of the country's electricity demand, he said. 

Currently, the authorities are supplying 1320 MW of electricity generated from the two units of this power plant to the national grid. 

Payra Thermal Power Plant is located at Dhankhali union under Kalapara upazila of Patuakhali district.
 

  • Latest
  • Most Viewed
Lavrov meets Xi in Beijing: Russian state media
Unreleased Beyonce music stolen from car in Atlanta
World Bank VP meets CA, praises interim govt's economic steps
US imposes 17% duty on most Mexican fresh tomatoes
Divided EU weighs action against Israel over Gaza war
Argentine monthly inflation inches up, still low
US probes drones and polysilicon imports, opening door to tariffs
Starc inspires Australia as West Indies all out for 27
US House set to vote on landmark crypto bills this week
NBA Sixers forward George undergoes left knee surgery
১০