DHAKA, Oct 8, 2025 (BSS) - The overall construction progress of the extended 1.16 km metro line from Motijheel to Kamalapur has so far reached 64.23 percent.
"The physical work for the Motijheel-Kamalapur section of the Dhaka Metro Rail project is progressing fast," a Metro Line-6 project official told BSS here today.
He said the authorities are expecting to complete the 1.16-kilometre metro rail track from Motijheel to Kamalapur by next year, as work on extending MRT Line-6 is going on in full swing.
According to the metro project, the extended section of the entire elevated metro rail is expected to commence operations next year, as the authorities focused of intense construction activities, including agreements for installing electrical and mechanical systems.
As of September 30, 2025, the actual average progress of the Uttara Uttar-Motijheel section reached 99.43 percent, while the Motijheel-Kamalapur section recorded 64.23 percent.
According to project details, construction of all station columns has been completed, while all 298 precast segments have been finished at the construction yard.
So far, 22 out of 27 spans have been installed, and the total length of the concourse roof (180 metres), track slabs, and platform slabs has been completed. The project details also said that all 824 precast parapet walls have been installed.
The total length of Bangladesh's first Mass Rapid Transit (MRT) Line from Diabari-Mirpur-Farmgate-Motijheel-Kamalapur is 21.26 kilometres. Commercial operation of the metro rail from Uttara to Motijheel began in November 2023.
Now the last train leaves from Uttara at 9-pm, and from Motijheel at 9:40-pm, while on Friday the schedule of metro train is the first train leaves from Uttara at 3-pm and the last train from Motijheel at 9:40pm.
On an average, each train having six coaches can travel 2,300 passengers at a time.